Timelapse clips

View our dynamic Timelapse clips, released on a monthly basis. It is a one minute video which is built only with multiple cameras with timelapses views and comparative views during a specific calendar period.

December 2022

 

October 2022

Windows and clean air conditioning

November 2022

Windows, ventilation and resin coating

August 2022

Starting indoor work

September 2022

Windows and air conditioning

June 2022

Clean Room floor construction

July 2022

Floors finalization

April 2022

First Floor building

May 2022

Pylons installation

February 2022

CMC drilling

March 2022

First floor pouring - Precast pannels

December 2021

Removing plantation - Wall destruction

January 2022

Pipe network construction - CMC preparation